This page
reports on progress at the Fair Play children’s hostel during 2005.
For the last three
years we have been refurbishing the Fair Play hostel in
Three teams have
worked at the hostel this year. The dates for first team of 17 people were 27
May to 4 June, and the second team of 13 people were 3 to 11 June, some people
are covering both weeks. A third team of
11 people worked at Fair Play from 15 to 22nd October.
October 2005
This is what the
October team achieved.
They completed the
roof by sealing it to the insulation on the walls.
23 radiators
fitted:
The kitchen on the
ground floor gutted and tiled:
Painting jobs in
the toilet/ shower rooms:
And still found
time to have fun with the children!
The first two
teams have returned from their hard work at the Fair Play hostel. There are 21 rooms on the top floor. 11 are bedrooms, 3 are wash rooms, 4 are
store rooms, and 3 are used as a dance studio.
For all the rooms
the two teams managed to:
-
install
lights and power sockets
-
fit, sand,
stain and varnish all the doors
For the 11
bedrooms:
-
scrape,
plaster and paint the walls and ceilings
-
clean
windows, frames and floors
-
hang curtains
and lay carpets
For the 3
washrooms
-
water pipes installed
ready for plumbing
-
two shower/
toilet rooms tiled and a start made on tiling the floor
-
the wash room walls and floor tiled.
Staff
give tuition We work with the young
people
Two girls pleased
with their new room.