This page
reports on progress at the Fair Play children’s hostel during 2004. The most recent report is at the top, with
previous ones below.
As a result of a successful
programme of fund-raising during 2003 and the early part of 2004, we decided
that we could accelerate progress with the refurbishment programme at the Fair
Play hostel by sub-contracting some of the work. We have had the roof sealed, the outside walls sealed, insulated
and painted and the remaining windows double-glazed.
Three teams have
been working in the hostel: from 29th May to 5th June,
from 19th June to 27th June and from 23rd to
30th October. All team
members paid their own flight and accommodation costs. All the money we raise goes direct to
refurbishing the Fair Play hostel.
In the previous
two years we had completed the girls (first) floor and the boys (second) floor
and made a good start on the third floor.
The objective for 2004 was to complete the third and fourth floors. At the end of 2004 we can report that most
bedrooms on all four of the children’s floors are now in very good
condition.
For 2005 there are
shower and toilet rooms on the fourth (top) floor to be tiled and equipped.
There is also some decorating to be done elsewhere.
The third team has
returned. They concentrated on the
electrics and the decoration of the rooms on the third and fourth floors.
We have just
received this picture showing progress on refurbishing the outside walls of the
Fair Play hostel. The picture also
shows the completed double glazed windows.
By contrast, there’s a glimpse of one of the neighbouring buildings
reminding us of what the hostel was like.
The May and June
teams, each comprising 11 members, have worked for a week at the Fair Play
hostel, and considerable progress can be reported.
All windows are now double-glazed.
Scaffolding has
been erected along one of the outside walls.
Insulation is being fixed to the wall. This is then covered with a
fibreglass mat and a cement-like screed.
Finally the walls will be painted pale blue with bright yellow
highlights between the windows.
Work is due to
start in July on sealing the roof.
On
the third floor, most of the bedrooms are finished and some occupied.
All rooms have
power and light fittings.
The washroom and
both bathroom walls are now tiled. The
hostel workman and some of the teenagers helped us with the preparation and
tiling.
One bathroom has
all the fittings but the other still has to be done. The floors of the two bathrooms and the washroom still need
tiling.
On the fourth
(top) floor the walls and floors of the two bathrooms and the washroom have
been cemented ready for tiling.
The old door
frames on the fourth floor have been removed in preparation for new ones.
A start has been
made on the electrics.
Manchester United
generously donated sweatshirts and jackets.
Football coaching sessions for the teenagers and also for the younger
children took place in the playground of a local high school each morning.
All the computers
that Procter & Gamble donated were checked and where necessary mended. They are used by some for homework but are
more popular for games!
New
material was bought for curtains and some of the girls helped us with the
cutting out.
In the afternoons,
the ladies made 40 curtains, ready for the fourth floor bedrooms.
There are three
working sewing machines in the sewing room we made in 2002.
Every morning the
ladies organised art and craft activities and singing games with the younger
children.
All three teams
exceeded what they had hoped to achieve.
We very much
enjoyed working with the children, and they with us.